Yearly report 2011

Русская версия

Implementing an automated data measurement system for commercial electricity metering

The programme to modernise the automated data measurement system for commercial electricity metering at Kubananergo stipulates developing these automated systems at the Company’s substations along borders with neighbouring consumers/subjects of the wholesale electricity market (Expanding the Automated Data Measurement System for Commercial Electricity Metering of the Third Stage of the Exterior Perimeter at Kubanenergo). In 2011 within this programme construction and fitting work was carried out to install missing meters for current and tension transformers.

In view of the development of an automated system for commercial electricity metering in the district distribution networks the following work was carried out in the accounting year:

In 2012 the Kubanenergo investment programme in view of the development of automated metering systems plans to carry out construction and fitting work in accordance with the following project: