Yearly report 2011

Русская версия

Areas and structure of capital investment

The main area of realisation of the investment programme at Kubananergo in 2011 was capital investment in technical refitting and renovation (60.8% of total capital investment) and new construction of energy facilities (39.1%).

of total investments for 2011 4 542.73 million rubles was invested in capital assets, including:

Capital investment structure in 2011, in millions of rubles

Fixed capital formation in 2011

Area of capital investment Amount, in millions of rubles
Technical refitting and renovation 2 761.7
including on Olympic facilities 605.1
New build 1 776.9
including Olympic facilities 1 321.6
Other (acquisition of fixed assets) 4.1
Total 4 542.7
including Olympic facilities 1 926.6

The largest energy facilities brought into operation in 2011 following renovation

Facility Renovation work carried out Amount, in millions of rubles
Sochi 110/6 kilovolt substation in Sochi Replacing 25 MVA transformers with two 40 MVA transformers (second stage of start up facilities completed) 75.1
Alpiiskaya 110 kilovolt substation in Sochi Replacing 16 MVA transformer with 25 MVA transformer and installing a second 25 MVA transformer with renovation of a 110 kilovolt outdoor switchgear with 110 kilovolt overhead lines in Sochi 123.8
110 kilovolt power lines adjacent to Vishesteblievskaya 220 kilovolt substation in Vishesteblievskaya village, Temryuk District Renovation of existing 110 kilovolt power lines and running them to the 220 kilovolt Vishesteblievskaya substation constructed 203.3
Varenikovskaya-Gostagaevskaya 110 kilovolt power line between Varenikovskaya in Krimsk District and Gostagaevskaya village near Anapa Renovation of 110 kilovolt main power line with replacement of line with larger cross section and installation of multi-sided utility poles 183.1
Anapskaya 110 kilovolt substation in Anapa Expansion of the substation and installation of a third transformer with a capacity of 25 MVA as part of executing a decision by Krasnodar Region headquarters on electricity supply safety and the programme for preparations for the autumn and winter period 2011-2012. 185.5

The largest energy facilities added to fixed assets in 2011 as new construction

Facility Short description Amount, in millions of rubles
Vishnevaya 110/10/10 kilovolt substation in Sochi (Olympic facility) Brought into operation in 2010 and  added to fixed assets after title documents were drawn up on 2011 406.5
Praskoveevka 110/10 kilovolt substation in Gelendzhik Substation with installation of 10 MVA transformer and 24 kilometre overhead 110 kilovolt power line 133.7
Vishesteblievskaya 110 kilovolt substation in Temryuk District Tow single circuit 110 kilovolt power lines running for 55.89 kilometres with fibre optic communication channels 268.1

Investment projects begun in 2011

Investment project Planned year of start of operations
Construction of transmission line approach (110 kilovolt) to transmit capacity from Adler thermal station to existing line from Yuzhnaya substation to Adler substation (Olympic facility) 2013
Renovation of the Gostagaevskaya-Dzhemete and Varenikovskaya village in Krimsk District and Anapa 110 kilovolt power lines 2012
Creating an integrated online monitoring system for safety at Olympic facilities 2012